Ghana: ECG Assures Customers of Power Stability

  • ECG assures customers of electricity supply amidst planned maintenance.
  • The utility has commenced the reconstruction of transmission lines.

The Electricity Company of Ghana (ECG) and the Ghana Grid Company Limited (GRIDCo) have assured citizens that the ongoing maintenance works in Accra will not lead to power outages. This followed reports that Accra was about to experience power outages due to the commencement of the reconstruction of transmission lines from Achimota to Mallam substations.

A joint statement issued in Accra noted that the reconstruction works commenced last Saturday, April 9. “Our attention has been drawn to press reports with headlines such as “dumsor” to hit Accra for 84 days in reference to a public statement issued by GRIDCo. Whilst we confirm the reconstruction work on our transmission lines had commenced on Saturday, April 9, 2022, we wish to assure the public that the ongoing work will not lead to any “Dumsor,” the statement noted.

It said that Phase One of the reconstruction exercise of the transmission line from Mallam Substation to Avenor was undertaken and completed in November 2021 without any significant disturbance to power delivery in Accra and its environs.

Phase Two of the exercise from Achimota Substation to Avernor, the statement added, would similarly not disrupt power delivery in Accra. It stated that as part of measures to improve power delivery in Accra and its environs, GRIDCo and ECG had inaugurated the Pokuase and Kasoa Substations.

The statement indicated that the bulk supply points of Kasoa, Mallam, Accra Central, Pokuase and Achimota Substations had enough transformer capacities to meet the desired demand without any load curtailment or load shedding. It further assured Ghanaians that GRIDCo and ECG are collaborating effectively to deliver power whilst the reconstruction work goes on.

 