Uganda, Rwanda Commence Power Connectivity Project

  • Projects for power connectivity between Uganda and Rwanda are back on – profiting from warming relations between the two sides, as are some projects meant to enhance the East African power pool.
  • Uganda plans to connect its grid to Kenya at Malaba, DR Congo at Mpondwe, South Sudan at Nimule and Tanzania at Mutukula.

Uganda and Rwanda have since 1995 been exchanging power at the Cyanika border, which serves Kisoro in Uganda and Gatuna. Projects for power connectivity between Uganda and Rwanda are back on – profiting from warming relations between the two sides, as are some projects meant to enhance the East African power pool.

Uganda’s Energy Ministry Permanent Secretary Irene Pauline Batebe told The EastAfrican, “Commissioning of the Uganda-Rwanda line awaits installation of communication boosters on the Rwandan side.” The Rwanda-Uganda high-voltage power trading was expected to start in 2020. Completion of the project will see the power exchange rise from the current 2MW to over 200MW.

Richard Okou, the technical director of Uganda’s Electricity Regulatory Authority, says the two sides are awaiting the installation of adequate electrical equipment and a linkage for communication. The two countries have since 1995 been exchanging power at the Cyanika border, which serves Kisoro in Uganda and Gatuna. Both countries produce more energy than they can consume, although they are constrained by low power distribution networks. On the Rwandan side is the 220/110kV Shango substation, described as a strategic infrastructure to interconnect the electric grids of Rwanda, DR Congo, Tanzania and Uganda. It was commissioned in 2019.

Uganda has powered its line up to the Mirama Hills interconnection point. It plans to connect its grid to Kenya at Malaba, DR Congo at Mpondwe, South Sudan at Nimule and Tanzania at Mutukula. However, the construction of high-voltage overhead transmission lines in the neighbouring countries stalled, making it difficult for Uganda to export its power.

These projects form the wider Eastern African Power Pool Power (EAPP), a projection of the future linkages between various power grids. An EAPP analysis of expected trends from 2021 to 2030 published in 2021 indicates that many countries have difficulties fulfilling a reserve margin of 15 per cent of power supply solely via national generation, while others have excess with poor distribution. And data from the Uganda Electricity Regulatory Authority show that as of December 2021, Uganda’s installed electricity reached 1,346 megawatts (MW) with demand at 800 MW, leaving a surplus of 546 MW.

 

Leave a Reply

Your email address will not be published. Required fields are marked *